Sykes and Partners 10th Anniversary

Project Overview

Project

Project Name:

Offshore FPSO Spool Overhaul

Sector

Category:

Oil & Gas (Offshore EPC)

Standards

Ratings:

97

Safety

Safety Milestone:

Zero LTI (100% Safe Hours)

Location

Location:

Takoradi Yard & Offshore Ghana

Offshore FPSO Piping Spool Overhaul

During a planned turnaround maintenance campaign for a Tier-1 multinational upstream operator in Ghana's offshore basin, Sykes and Partners was awarded the turnkey contract to engineer, prefabricate, inspect, and install high-pressure process piping spools and critical isolation valve assemblies aboard an active Floating Production Storage and Offloading (FPSO) vessel.

Operating within a high-stakes shutdown timeline where every unbudgeted hour translates to major production shut-in costs, Sykes and Partners leveraged its 7,514m² commercial fabrication yard in Takoradi for end-to-end spool prefabrication, hydrotesting, and surface coating prior to offshore mobilization, delivering complete zero-defect installation four days ahead of client deadline.

Key Engineering Highlights

Precision fabrication and stringent quality controls executed in full compliance with ASME and API international codes.

Laser Metrology

3D Laser Metrology

Pre-shutdown dimensional scanning achieved millimeter-exact tie-in tolerances.

Takoradi Yard Prefab

Takoradi Yard Prefabrication

90% of welding, NDT, and hydrotesting completed off-site to reduce offshore hot-work.

Zero Rework

100% NDT Acceptance

Zero weld reject rate across all radiography and ultrasonic examination.

Turnaround Execution Workflow

Our systematic execution methodology ensures critical path control from engineering surveys through offshore handover.

01

Survey & Material Procurement

Laser dimension survey offshore; procurement of API 5L Grade B, Duplex stainless steel, and API 6D ball valves with 3.1 mill certs.

02

Yard Fabrication & Hydrotesting

WPS/PQR qualified welding, 100% radiographic & ultrasonic testing, hydrostatic pressure test to 1.5x design pressure, and marine coating.

03

Offshore Rigging & Final Tie-In

Barge transport to offshore field, crane rigging, cold-cut spool removal, flange torqueing with calibrated hydraulic tensioners, and leak testing.

Engineering Challenges & Solutions

How Sykes and Partners engineered solutions to mitigate critical path risks in live offshore hydrocarbon facilities.

Technical Challenges:

Extreme Time Constraints:

Fixed 72-hour mechanical shutdown window with severe liquidated damages.

Hazardous Gas Environment:

Restricted hot-work permitting due to adjacent live hydrocarbon processing units.

Aggressive Marine Corrosion:

Severe marine atmospheric corrosion requiring specialized barrier protection.

Sykes and Partners Solutions:

Offsite Prefabrication Strategy:

Fabricated 14 complete spools in Takoradi Yard, cutting offshore installation hours by 65%.

Cold-Work Flange Alignment:

Utilized pressurized cold-cutting and calibrated hydraulic flange spreaders eliminating spark hazards.

ISO 12944 Protective Coating:

Applied 3-coat NORSOK M-501 compliant epoxy barrier system ensuring 20-year operational life.

Technical Questions About This Project

All welding followed ASME Section IX qualified GTAW (TIG) root passes with SMAW fill and cap using low-hydrogen consumables, certified by third-party classification societies.

Through comprehensive Job Safety Analyses (JSA), dedicated offshore HSE advisors, continuous atmospheric gas monitoring, and full compliance with OPITO offshore safety standards.

Contact our commercial team via our RFQ form or call our Labone office at +233 30 273 3459 to discuss your shutdown schedule and project scope.